network2017 [2017-01-13 11:56] – tim | network2017 [2017-01-15 16:20] – [New Rack layout] tim | ||
---|---|---|---|
Line 23: | Line 23: | ||
* Hacklab secondary switch can move to mid-rack and be used for servers | * Hacklab secondary switch can move to mid-rack and be used for servers | ||
* Replacement Hacklab router (assuming a 1U full-depth) can go mid-rack | * Replacement Hacklab router (assuming a 1U full-depth) can go mid-rack | ||
+ | * fit two high-capacity PDUs, attached to different circuits | ||
+ | * < | ||
+ | * e.g. 2x 12x IEC [[http:// | ||
==== New Shelf layout ==== | ==== New Shelf layout ==== | ||
Line 30: | Line 32: | ||
* Tower PCs can go on front shelf, Raspberry Pis and console can go on back-shelf | * Tower PCs can go on front shelf, Raspberry Pis and console can go on back-shelf | ||
* More power strips | * More power strips | ||
- | * Use a single Anker power supply or 2-3 Ikea USB chargers to reduce cabling | + | * Use a single Anker power supply or 2-3 Ikea USB chargers to reduce cabling |
* Use a dumb gigabit switch to reduce network cabling (Server LAN only, special cases can keep connecting to the rack switch) | * Use a dumb gigabit switch to reduce network cabling (Server LAN only, special cases can keep connecting to the rack switch) | ||
Line 40: | Line 42: | ||
Need to: | Need to: | ||
- | * Identify suitable back-boxes for cable conduit | + | * Identify suitable back-boxes for cable conduit: [[http:// |
* Purchase back-boxes, twin sockets, additional cable | * Purchase back-boxes, twin sockets, additional cable | ||
+ | * 3x twin backboxes (plus 2x twin and 1x single spares for future projects) | ||
+ | * 3x http:// | ||
+ | * 2.5mm multipack: http:// | ||
* Arrange access to plant room to switch-off power | * Arrange access to plant room to switch-off power | ||
* Schedule downtime (can be mitigated by running essential systems from another circuit) | * Schedule downtime (can be mitigated by running essential systems from another circuit) | ||
Line 47: | Line 52: | ||
==== New Router ==== | ==== New Router ==== | ||
- | Ideal configuration would be a Dell R610 with two power supplies. RAM requirement is modest (4GB). Disks should be modest but hardware RAID1. | + | Ideal configuration would be a Dell R610 with two power supplies. RAM requirement is modest (1G). |
- | Software is likely to be VyOS, BSD-RP or other router environment. | + | Software is likely to be BSDRP. |