Tasks
These tasks can be started now:
- Order/source a combined euro-profile and handle for door.
- Run 4 cat5 cables from G11 rack to G14 roof space
Install UniFi access pointOrder new legs for sink unit- Fit benches
Straighten the wavy worktopAttach wooden battens to the wall to support the back of the worktopsChamfer the worktop edgesSand & oil the worktopsCoat 1Coat 2Coat 3
Attach legs and fit the worktops, attaching them to the battens with L brackets - slotted so they can move up and down a bit(?)- Install more battens to support the worktop corner/edge [only if needed]
- Find wood to make shelves (mostly 30cm depth, but some deeper for the PSU and function generator)
- Sort/tidy/prepare electronics components for the move
Shelves
The vertical brackets are installed but we will need to order more horizontals, and to source the shelf boards. Given the amount of worktop that we will be removing from G1 later on, it might be worth installing only a limited amount of shelving for now instead of buying new material.
On the narrow end of the room, above the component drawers:
- 3 of 226cm x 30-31cm (slightly less than 226 to allow for the conduit).
To the left of the window:
- 150cm x 54cm (for the function generator and HP power supply)
- 150cm x 25-30cm (for oscilloscope, soldering tools, etc)
On the long wall:
- Many of ~290cm x 30cm (general storage)
- ~290cm x 25-30cm (for oscilloscope, soldering tools, etc)
To the right of the sink, attached to wall and sink unit:
- Recessed shelf for PCB etch tank.