====== G1 Refurbishment ====== | ====== G1 Refurbishment ====== | ||
- | The general plan of refurbishment of G1 (the main room) is to make it suitable for larger groups of people. It is also desirable to create both, working | + | The general plan of refurbishment of G1 (the main room) is to make it nicer and more welcoming. |
{{: | {{: | ||
- | |||
- | ==== Decision making section ==== | ||
- | |||
- | |||
- | https:// | ||
- | | ||
- | |||
- | |||
- | |||
- | ==== Planning and timing section ==== | ||
- | |||
- | It involves the following stages with a very optimistic estimate of time: | ||
- | |||
- | | ||
- | |||
- | 1. move all the stuff out or G1 e-recycling waste – 0.5day - done | ||
- | 2. get rid of TV stand – 0.5day - done | ||
- | 3. remove the large flat table from the middle of the room - 1day | ||
- | 4. Decide which linoleum to get – 3 days | ||
- | 5. Remove the cupboard from G1 and probably turn it into a members box holder in G11 1 day + place for keeping it – 1.5 days | ||
- | 6. remove all the floor - 1day | ||
- | |||
- | Resources necessary: 5.5days of 2-3 people and 2 days of 4 people | ||
- | |||
- | Flooring stage | ||
- | |||
- | 1. Buy all the glue, plaster, paint and linoleum and store it in the corridor – 2days max | ||
- | 2. prepare the floor with all necessary plastering, leveling and stuff. - 2 days 4-5 people | ||
- | 3. Glue the linoleum to the floor – 2-3 days 4-5 people | ||
- | 4. Prettify all the bits and bobs – 2-3 days 2-3 people | ||
- | |||
- | Resources necessary: 2days of 1-2persons after that 4-5days of 4-5 people and 2-3 days of 2-3 people | ||
- | |||
- | Furniture stage | ||
- | |||
- | 1. Turn the FM station to the other wall and add small tools and soldering corner – 1 day | ||
- | 2. Make or buy the hexagonal tables - 3days | ||
- | 3. Make or buy the divider shelf and mounts - 1-2days | ||
- | 4. Make the electronic components, enterntainment, | ||
- | | ||
- | Resources necessary: 1day of 1-2 person, 3 days of 2people, 1-2days of 2 people, 2-3 days of 2-3 people. | ||
- | |||
- | |||
- | |||
- | |||
- | === Some floor options === | ||
- | |||
- | G1 has 40sq meter area max | ||
- | |||
- | |||
- | |||
- | Garage flooring tiles - fixable, water-resistant, | ||
- | |||
- | cost £30-35 per sq meter inc VAT = total £1200-1400 | ||
- | |||
- | https:// | ||
- | |||
- | {{: | ||
- | |||
- | |||
- | |||
- | Linoleum - not fixable, water resistant, no need for floor leveling: | ||
- | |||
- | cost £19 per sq meter exc VAT = total £800-1000 | ||
- | |||
- | https:// | ||
- | |||
- | {{:: | ||
- | |||
- | |||
- | |||
- | Laminate flooring (we need AC5 wear rating, suitable for commercial use in shops) | ||
- | |||
- | cost £14 per sq meter inc VAT = total £560 | ||
- | |||
- | https:// | ||
- | |||
- | {{: | ||
- | |||
- | |||
- | Carpet tiles - absorbs spilled liquid and slightly harder to clean, and may generate static electricity. That the only problem. | ||
- | |||
- | £10 per sq meter inc VAT = total £400. | ||
- | |||
- | https:// | ||
- | |||
- | {{: | ||
- | |||
+ | ==== Planning ==== | ||
+ | 2do: | ||
- | === Furniture | + | - Prep G1 for flooring people |
+ | * Move everything out of the room (includes clearing the fridge, dishwasher etc.) | ||
+ | * Remove old linoleum | ||
+ | * Remove coathanger board | ||
+ | * Pay final 50% of flooring cost | ||
+ | - Order/make new tables | ||
+ | - ??? | ||
+ | ==== Cost ==== | ||
+ | - Floor: 1602 | ||
- | Ikea Kallax Shelving unit - 182x182cm £150 | ||
- | https:// | ||
- | {{: |