Both sides previous revisionPrevious revisionNext revision | Previous revisionNext revisionBoth sides next revision |
todo [2019-10-30 00:42] – formatted roundup archive as table MirZa | todo [2020-01-30 12:40] – just_ben1996 |
---|
* G1 hifi shelves: replace the short brackets with long brackets (we have a surplus and the shelf would be more secure). | * G1 hifi shelves: replace the short brackets with long brackets (we have a surplus and the shelf would be more secure). |
* Laser Cutter #1: Connect the air-flow sensor into the safety loop (in series with the lid switch, water flow sensor, etc). | * Laser Cutter #1: Connect the air-flow sensor into the safety loop (in series with the lid switch, water flow sensor, etc). |
* Move G6 (Al's room) access point to G11. | |
| |
| |
* Pull additional Cat5 cables from between G11 and G14. | * Pull additional Cat5 cables from between G11 and G14. |
* Specify and purchase shelving for G14 (full-lengths, 300mm depth). | * Specify and purchase shelving for G14 (full-lengths, 300mm depth). |
* Install spur for G1 water heater. | |
* Tidy-up the radio corner. | * Tidy-up the radio corner. |
===== Infrastructure Projects ===== | ===== Infrastructure Projects ===== |
| 54 | 2017-12-08.15:50:13 | Create training docs for mitre saw | 4 | None | 1 | | | 54 | 2017-12-08.15:50:13 | Create training docs for mitre saw | 4 | None | 1 | |
| 52 | 2017-12-08.15:49:11 | Create training docs for table saw | 4 | None | 1 | | | 52 | 2017-12-08.15:49:11 | Create training docs for table saw | 4 | None | 1 | |
| 39 | 2019-03-09.18:45:32 | "Update ""Facilities"" page on the website" | 19 | None | 3 | | |
| 56 | 2018-08-04.18:02:06 | Create training docs for bantam lathe | 4 | None | 3 | | | 56 | 2018-08-04.18:02:06 | Create training docs for bantam lathe | 4 | None | 3 | |
| 17 | 2018-06-28.15:45:34 | Tidy roof radio/network equipment | 3 | None | 3 | | | 17 | 2018-06-28.15:45:34 | Tidy roof radio/network equipment | 3 | None | 3 | |
| 73 | 2018-04-27.12:15:35 | Maintenance on Block B roof ladder | 3 | None | 1 | | | 73 | 2018-04-27.12:15:35 | Maintenance on Block B roof ladder | 3 | None | 1 | |
| 88 | 2018-04-24.18:02:49 | Set up PC for the CNC router | 4 | None | 1 | | |
| 87 | 2018-04-24.18:00:42 | CNC router z-axis counterweight or brake | 4 | None | 1 | | |
| 85 | 2018-04-24.17:56:03 | CNC router dust extraction | 4 | None | 1 | | |
| 84 | 2018-04-24.17:55:39 | CNC router power/e-stop wiring | 4 | None | 3 | | |
| 82 | 2018-04-24.17:47:53 | Watercooling for the CNC router | 4 | None | 1 | | |
| 79 | 2018-04-14.20:48:15 | Fix Ultimaker 2 LED Strips | 23 | None | 1 | | | 79 | 2018-04-14.20:48:15 | Fix Ultimaker 2 LED Strips | 23 | None | 1 | |
| 70 | 2018-01-26.03:13:28 | Fix CNC spindle probe | 4 | 4 | 5 | | |
| 11 | 2018-01-19.00:04:51 | Repair Tektronix oscilloscope | 3 | None | 3 | | | 11 | 2018-01-19.00:04:51 | Repair Tektronix oscilloscope | 3 | None | 3 | |
| 18 | 2018-01-04.22:31:50 | Dismantle digital waterfall | 3 | None | 5 | | | 18 | 2018-01-04.22:31:50 | Dismantle digital waterfall | 3 | None | 5 | |
| 33 | 2017-06-28.00:23:48 | Organise chemical storage and COSHH docs | 3 | None | 1 | | | 33 | 2017-06-28.00:23:48 | Organise chemical storage and COSHH docs | 3 | None | 1 | |
| 32 | 2017-06-27.23:46:31 | Organise cleaning cupboard | 3 | None | 1 | | | 32 | 2017-06-27.23:46:31 | Organise cleaning cupboard | 3 | None | 1 | |
| 4 | 2017-04-24.14:00:20 | Fix the NovaTurn CNC lathe | 4 | None | 1 | | |
| 76 | 2019-06-09.10:00:41 | NFC tool lockers | 3 | None | 3 | | |
| 21 | 2018-06-03.18:42:30 | Tool access controllers | 3 | 3 | 5 | | |
| 97 | 2018-06-03.09:28:59 | Membership Policy | 21 | 21 | 1 | | | 97 | 2018-06-03.09:28:59 | Membership Policy | 21 | 21 | 1 | |
| 28 | 2018-05-22.09:46:27 | Close out the milling pledge | 4 | None | 5 | | | 28 | 2018-05-22.09:46:27 | Close out the milling pledge | 4 | None | 5 | |
| 67 | 2018-05-01.19:57:43 | Remote antenna switch for roof->g1 downlink | 3 | None | 3 | | | 67 | 2018-05-01.19:57:43 | Remote antenna switch for roof->g1 downlink | 3 | None | 3 | |
| 89 | 2018-04-25.13:30:09 | Mailman 3 mailing lists | 3 | 3 | 3 | | | 89 | 2018-04-25.13:30:09 | Mailman 3 mailing lists | 3 | 3 | 3 | |
| 24 | 2018-04-13.09:54:56 | Automated do-not-hack stickers | 3 | 3 | 3 | | |
| 20 | 2018-01-26.14:54:24 | Deploy Loomio for trial | 3 | 3 | 3 | | | 20 | 2018-01-26.14:54:24 | Deploy Loomio for trial | 3 | 3 | 3 | |
| 104 | 2019-05-17.14:30:44 | (Sliding) doors under benches in G8 | 45 | None | 1 | | | 104 | 2019-05-17.14:30:44 | (Sliding) doors under benches in G8 | 45 | None | 1 | |
| 102 | 2019-03-23.11:45:06 | test subject | 3 | 3 | 3 | | |
| 63 | 2018-12-18.14:30:07 | Build new test lead organisation fixture | 23 | None | 3 | | | 63 | 2018-12-18.14:30:07 | Build new test lead organisation fixture | 23 | None | 3 | |
| 69 | 2018-07-18.13:23:09 | SatNOGS station | 3 | None | 3 | | | 69 | 2018-07-18.13:23:09 | SatNOGS station | 3 | None | 3 | |
| 47 | 2018-04-28.15:54:46 | Test/fix reflow oven | 4 | None | 3 | | | 47 | 2018-04-28.15:54:46 | Test/fix reflow oven | 4 | None | 3 | |
| 92 | 2018-04-27.12:10:08 | Name Badge Printer / Visitor Sign In | 22 | None | 1 | | | 92 | 2018-04-27.12:10:08 | Name Badge Printer / Visitor Sign In | 22 | None | 1 | |
| 91 | 2018-04-27.12:03:35 | Hot Water for G1 | 3 | None | 3 | | |
| 90 | 2018-04-25.14:42:53 | Consumables Inventory | 23 | None | 3 | | | 90 | 2018-04-25.14:42:53 | Consumables Inventory | 23 | None | 3 | |
| 83 | 2018-04-24.18:17:54 | Spindle/VFD control from LinuxCNC | 4 | None | 1 | | |
| 86 | 2018-04-24.18:17:45 | Tool touchoff pad for the CNC router | 4 | None | 1 | | |
| 61 | 2018-03-31.05:57:11 | Build new terminal unit for HP bench power supply | 3 | None | 3 | | | 61 | 2018-03-31.05:57:11 | Build new terminal unit for HP bench power supply | 3 | None | 3 | |
| 26 | 2018-03-03.01:07:58 | Install roof-top weather station | 3 | 10 | 3 | | | 26 | 2018-03-03.01:07:58 | Install roof-top weather station | 3 | 10 | 3 | |
| 59 | 2018-02-02.15:45:46 | Replace taps in G8 and G11 | 21 | None | 3 | | |
| 60 | 2018-01-25.15:21:14 | Obtain BNC cables and such for Oscilloscope/Signal Generators | 23 | None | 3 | | | 60 | 2018-01-25.15:21:14 | Obtain BNC cables and such for Oscilloscope/Signal Generators | 23 | None | 3 | |
| 58 | 2018-01-03.00:14:14 | Purchase vacuum desoldering pump | 3 | None | 1 | | | 58 | 2018-01-03.00:14:14 | Purchase vacuum desoldering pump | 3 | None | 1 | |
| 30 | 2017-06-11.16:09:24 | 3D Printing Supplies | 15 | 15 | 1 | | | 30 | 2017-06-11.16:09:24 | 3D Printing Supplies | 15 | 15 | 1 | |
| | 70 | 2018-01-26.03:13:28 | Fix CNC spindle probe | 4 | 4 | 5 | |
| | 87 | 2018-04-24.18:00:42 | CNC router z-axis counterweight or brake | 4 | None | 1 | |
| | 83 | 2018-04-24.18:17:54 | Spindle/VFD control from LinuxCNC | 4 | None | 1 | |
| | 86 | 2018-04-24.18:17:45 | Tool touchoff pad for the CNC router | 4 | None | 1 | |
| | 59 | 2018-02-02.15:45:46 | Replace taps in G8 and G11 | 21 | None | 3 | |
| |
| (Mostly) Done tasks |
| ^ id ^ activity ^ title ^ creator ^ assigned to ^ status ^ |
| | 4 | 2017-04-24.14:00:20 | Fix the NovaTurn CNC lathe | 4 | None | 1 | |
| | 102 | 2019-03-23.11:45:06 | test subject | 3 | 3 | 3 | |
| | 39 | 2019-03-09.18:45:32 | "Update ""Facilities"" page on the website" | 19 | None | 3 | |
| | 88 | 2018-04-24.18:02:49 | Set up PC for the CNC router | 4 | None | 1 | |
| | 85 | 2018-04-24.17:56:03 | CNC router dust extraction | 4 | None | 1 | |
| | 84 | 2018-04-24.17:55:39 | CNC router power/e-stop wiring | 4 | None | 3 | |
| | 82 | 2018-04-24.17:47:53 | Watercooling for the CNC router | 4 | None | 1 | |
| | 76 | 2019-06-09.10:00:41 | NFC tool lockers | 3 | None | 3 | |
| | 21 | 2018-06-03.18:42:30 | Tool access controllers | 3 | 3 | 5 | |
| | 24 | 2018-04-13.09:54:56 | Automated do-not-hack stickers | 3 | 3 | 3 | |
| | 91 | 2018-04-27.12:03:35 | Hot Water for G1 | 3 | None | 3 | |