G1 Refurbishment
Planning
The Plan™
Get the floor done while the lab is closed. Rip almost everything out of G1. Move in only the necessary bits.
2do
- Prep G1 for flooring people
- Create schedule for work
- Move everything out of the room (includes clearing the fridge, dishwasher etc.)
- Remove old linoleum
- Remove coathanger board
- Pay final 50% of flooring cost
- Order/make new tables
- Get a second sofa & coffee table
- Get a bookshelf
- Clean up the kitchen
- Clean floor
- Level floor?
- Remove old rubbish
- Get new chairs (aerons)
- Get notice board
- Make better kitchen
- Make tables
- ???
- Find (maybe) a designer to help
- Research improving ventilation
Questions
- How do we organise work to maintain social distancing?
- Should we have a mezzanine?
- How do we make the shelf movable?
Cost
- Floor: 1602