G1 Refurbishment

The general plan of refurbishment of G1 (the main room) is to make it nicer and more welcoming.

See Also

Planning

The Plan™

Get the floor done while the lab is closed. Rip almost everything out of G1. Move in only the necessary bits.

2do

  1. Prep G1 for flooring people
    • Move everything out of the room (includes clearing the fridge, dishwasher etc.)
    • Remove old linoleum
    • Remove coathanger board - River
    • Remove small projector & shelves - Marcin
    • Clean floor
    • Level floor - Costa
    • Call up flooring people and pay final 50% - Marcin
    • Remove desk supports
    • Remove lino skirting
  2. Inspect new shiny floor - everyone
  3. Order/make new tables - Costa
  4. Find a second sofa
  5. Find a coffee table
  6. Find nice chairs
  7. Figure out separator/shelf - Large Ikea Kallax obtained
  8. Order & hang notice board - Marcin
  9. Clean up walls
  10. Paint pipes and radiators and such to match walls
  11. Figure out better kitchen:
    • Cupboards
    • Utensils
    • Move everything into one box
    • Only communal cooking allowed for now
  12. Find (maybe) a designer to help - Marcin
  13. Research improving ventilation
  14. Remove wood strip from wall
  15. ???

Questions

Cool ideas

Theme ideas

Design Goals

What are we actually trying to achieve with the design?

How to make G1 Friendly

Meetings

07/03

Agenda:

Cost

  1. Floor: 1602

Butterfly latches: Adam Hall 17370C Butterfly latch keepers: Adam Hall 17370K

we need 32 latch+keeper sets for the tables

for “docking” the wheeled divider, we need four latches and eight latch keepers (for the two “docking ports”)