The general plan of refurbishment of G1 (the main room) is to make it nicer and more welcoming.

See Also

Planning

The Plan™

Get the floor done while the lab is closed. Rip almost everything out of G1. Move in only the necessary bits.

2do

  1. Prep G1 for flooring people
    • Move everything out of the room (includes clearing the fridge, dishwasher etc.)
    • Remove old linoleum
    • Remove coathanger board - River
    • Remove small projector & shelves - Marcin
    • Clean floor
    • Level floor - Costa
    • Call up flooring people and pay final 50% - Marcin
    • Remove desk supports
    • Remove lino skirting
  2. Inspect new shiny floor - everyone
  3. Order/make new tables - Costa
  4. Find a second sofa
  5. Find a coffee table
  6. Find nice chairs
  7. Figure out separator/shelf
  8. Order & hang notice board - Marcin
  9. Clean up walls
  10. Figure out better kitchen:
    • Cupboards
    • Utensils
    • Move everything into one box
    • Only communal cooking allowed for now
  11. Find (maybe) a designer to help - Marcin
  12. Research improving ventilation
  13. Remove wood strip from wall
  14. ???

Questions

  • How do we organise work to maintain social distancing?
  • Should we have a mezzanine?
  • Should we get a new projector screen (or fix old one)?

Cool ideas

  • Project show-off gallery
  • Figure out a theme

Theme ideas

  • Marine
  • Forest
  • Cyberpunk
  • Summer

Cost

  1. Floor: 1602